Airport Jet Bridge Project

Airport Jet Bridge Project

Roanoke Blacksburg Regional Airport

Installation of new Jet Bridge Caisson Footing, electrical service, and building main electrical switch gear upgrade. The total project time frame was 6 months. The concrete work associated with the project was expedited to be completed prior to cold temperatures of the winter months, while custom order materials and long lead items such as switch gear was being fabricated.

The installation of the new switch gear required maintaining the facility on backup generators 24 hours a day while completing the changeover.